Monday, 15 March 2004

Monday, 15 March 2004

Click on the thumbnails to see the full size picture.

Ralph working in the kitchen, removing the old electric baseboard.

In order to insulate the kitchen floor area (which is always chilly), Ralph pulled up the flooring, only to find a second floor beneath the first one, for reasons which are not clear.

By lunchtime, all the flooring has been pulled up, and there is insulation underneath but it's old and patchy, so new insulation is going in, stuffed into the crevices where we think the cold outside air has been getting in.

Kitchen area closet, where the FHW supply and return pipes will come up from the basement.

On the other side of the closet wall is the bathroom, where the old electric baseboard has been removed and a hole made for the FHW connection.

Looking down the kitchen stairwell, to the section of wallboard that's been removed for the supply and return piping.

By midafternoon, the plumber has run the supply and return piping. These are two views in the basement, showing the flexible aluminum-clad pipes brought to my Vaillant boiler.

Low, medium, and high views of the kitchen stairwell, showing supply and return piping now run through the wall and up to the kitchen closet.

Much of my day has been spent packing and moving stuff in the living room and office, where everything has to be moved away from the walls to allow access to the baseboards.

Go on to Tuesday 16 March